Painting of Taiaroa Head Lighthouse Dunedin
United Scaffolding Group Dunedin Branch installed scaffolding around Lighthouse for repaint by a Carus Professional Painting & Property Maintenance Operations crew. The work included scaffolding, plus Shrink-wrap around Lighthouse for the extreme weather conditions. Scaffold took 5 days to install and 2 days to wrap.
| Client: | Port Otago |
| Location: | Taiaroa Heads |
| Project Start Date: | 01/08/2023 |
| Completion date: | Estimated 19/09/2023 |
| Project Lead/ Manager: | Stuart Carse, Branch Manager Dunedin |